Bursztyn Unity has started sea trials. The first Świnoujście–Ystad voyage will take place as early as November.

Posted by Grzegorz
Category:

UPDATE September 29, 2026
Bursztyn Unity has started sea trials.
The new ferry is already at sea. This is another important milestone on the way to starting regular operations on the Świnoujście–Ystad route.

On September 28, 2026, at 5:30 a.m., Bursztyn Unity left Gdańsk Shipyard Remontowa and began her first sea trials.

The first phase of testing is expected to take about a week. Further trials are planned next, including tests with the classification society. Their successful completion will be one of the final steps before the vessel is handed over for operation.

START OF SEA TRIALS
28.09.2026
FIRST STAGE
~7 DAYS
SCHEDULED VOYAGE
November 2026

What is verified during sea trials?

During the first phase of sea trials, the most critical systems and the vessel’s handling at sea are tested. These tests allow for verification of the ferry’s readiness for the next stages of acceptance.

Propulsion and Machinery Systems
Verification of systems responsible for the vessel’s propulsion.
Navigation and Maneuvering
Verification of the ferry’s handling and equipment performance at sea.
Onboard and Communication Systems
Testing of equipment and systems essential for safe operation.

What’s next for Bursztyn Unity?

After completing the first phase of sea trials, the vessel is scheduled to return to the shipyard. Next, further sea trials are planned involving the classification society.

Following the completion of tests and acceptances, the ferry will be prepared for delivery to the shipowner. Concurrently, the crewing process for the vessel is underway.

The Path to the Maiden Voyage
28 September 2026
Start of sea trials
The Bursztyn Unity is leaving the Gdańsk Ship Repair Yard.
The next stage
Trials with the Classification Society
Following the first phase of testing, further trials and acceptances are scheduled.
11 November
Planned christening in Szczecin
The ceremony is due to take place at Wały Chrobrego.
November 2026
Planned inaugural crossing: Świnoujście–Ystad
The date of November 9, originally planned in the reservation systems, is no longer current due to the emergence of information that the ceremonial christening of the ferry is scheduled to take place on November 11, 2026.

ŚWINOUJŚCIE ↔ YSTAD
Bursztyn Unity is getting closer to her route

If all stages of trials and acceptances proceed according to schedule, the new vessel is set to commence regular operations on the Świnoujście–Ystad route.

Planning a crossing on the Świnoujście–Ystad route?

POL-AGENT is accepting inquiries regarding ferry crossing bookings. Contact us to plan your transport and check available shipping options.

VIEW FERRY CROSSING OFFER →

Updated: 29 September 2026. The dates regarding the commencement of operations are scheduled and may change depending on the progress of sea trials, acceptances, and the vessel’s preparation for service.
Bird's-eye view of the passenger-cargo ferry Bursztyn in Polsca livery, powered by LNG Hybrid, maneuvering in the port
Author: portalmorski.pl

Maiden Voyage Scheduled for November 2026

Bursztyn Unity, the second of the modern ferries being built for Polish shipowners, is getting closer to commencing regular operations on the Baltic Sea. According to the current POLSCA Baltic Ferries schedule, the vessel’s first planned departure from Świnoujście to Ystad will take place in November 2026. Prior to that, the ferry is scheduled to undergo sea trials and be officially christened in Szczecin.

Bursztyn Unity is set to soon join Jantar Unity as another modern ferry operating routes between Poland and Sweden. For the Port of Świnoujście and transport operators using ferry crossings, this marks a significant increase in transport capacity and another evolution in the organization of the POLSCA Baltic Ferries fleet.

Sea trials and christening ceremony in Szczecin

On September 28, 2026, the Bursztyn Unity left the Gdańsk Shiprepair Yard (Remontowa) and commenced her first sea trials. The first phase of testing is expected to last about a week. Afterwards, further trials are planned, including tests conducted with the participation of the classification society.

During the trials, systems and equipment being tested include the propulsion system, the vessel’s maneuverability, onboard systems, navigational equipment, and communication systems. The successful completion of all tests will be one of the final stages preceding the handover of the ferry for service.

The christening ceremony for Bursztyn Unity is scheduled for the first half of November 2026, just prior to its planned entry into regular service. The vessel is expected to dock at Wały Chrobrego in Szczecin and remain open to the media and the public for several days.

Bursztyn Ferry at the Shipyard – POL-AGENT Ferry Services & Maritime Freight Forwarding
Author: portalmorski.pl

Technical parameters – a high-capacity ferry for freight transport

Bursztyn Unity is a ro-pax ferry (roll-on/roll-off passenger ship) – a vessel modernly equipped for the transport of both passengers and heavy goods vehicles. Its specifications are impressive and reflect an advanced design:

Dimensions of the unit

📏 Length: 195,6 m
📐 Width: 32,2 m

Carrying capacity

👥 Passengers: ~400 osób
🚚 Lorry sets: ~270

📦 Load line: ~4100 metres
The massive cargo capacity enables the efficient transport of both passenger cars and trucks. This is one of the largest ferries operating on the Świnoujście–Ystad route.

Sister vessel Jantar Unity already in service on the route

Bursztyn Unity is a sister ferry to Jantar Unity, which has already entered regular service. In June 2026, Jantar Unity joined the Świnoujście–Ystad route and has since been offering passenger and cargo transport for road freight.

The introduction of Bursztyn Unity means:

✓ Increased sailing frequency
✓ Greater capacity for cargo transport
✓ Additional connections on the route

✓ Greater flexibility in transport planning
✓ Better conditions for price competition
✓ Higher reliability of the connection

Following the deployment of Bursztyn Unity on the route, a reorganization of the fleets and vessel assignments across POLSCA Baltic Ferries is also planned, including the Mazovia on the Świnoujście–Trelleborg route.

What does Bursztyn Unity mean for cargo transport?

4100m
Cargo lane metres

270
TIR Units

195,6m
Vessel length

400
Passengers

For carriers and logistics companies, the arrival of Bursztyn Unity on the Świnoujście–Ystad route means, above all:

Increased Space Availability
Thanks to 4,100 lane metres of cargo capacity, it is possible to plan the transport of even large fleets of vehicles in a single sailing.

More Flexible Planning
More sailings mean more options. It is easier to tailor transport to your logistical needs.

Better Competition and Prices
Additional transport capacity can translate into more competitive rates for cargo clients.

Greater Connection Reliability
If one ferry is undergoing maintenance, the other can replace or supplement the schedule.

Part of a broader fleet modernization project

Bursztyn Unity is not the final ferry in this series. A third vessel, Amber Unity, is also planned for delivery in 2029. Together, these three modern ferries of this class will form the core of POLSCA Baltic Ferries’ operational fleet.

Why follow the launch of Bursztyn Unity?

📈
More Space
An additional ferry means additional opportunities to accommodate vehicles on every sailing.

⏱️
Flexibility
More sailings = more flexible transport and logistics planning.

💰
Price competitiveness
Increased capacity can translate into more attractive rates for cargo.